Project Information

Industry

Educational Sector

Client

NUIG Student Accommodation

Colin Burke Electrical have been involved in this Design & Build project with JJRhatigan since it began earlier this year, in conjunction with JV Tierney & Co. Consulting Engineers. It comprises 4 multi-storey blocks of 674 bed spaces across 125 apartments in total.

We have been responsible for the installation of all electrical services including

  • MV Switchgear & transformer
  • PV Solar System 470KW
  • Fibre and data installation
  • Lighting general services
  • Access control system
  • Fire alarm
  • Disabled refuge
  • Building Management System (BMS) wiring.

Phase 1 is due for completion in January, with Phase 2 following shortly thereafter.